The system development life cycle (SDLC)is the traditional system development method for large IT projects,such as IT infrastructure or an enterprise system.

A) True
B) False

Correct Answer

verifed

verified

__________ determines if the required technology,IT infrastructure,data structures,analytics,and resources can be developed and/or acquired to solve the business problem.

Correct Answer

verifed

verified

Technical ...

View Answer

Postproject reviews,or _________,identify the reasons the project was successful or not,strengths and weaknesses of the project plan,how problems were detected and resolved,and how the project was successful in spite of them

Correct Answer

verifed

verified

Which of the following issues about the SDLC methodology is false?


A) Requirements analysis is critical to the success of the project.
B) System development practitioners agree that the more time invested in analyzing the current system and understanding problems that are likely to occur during system development,the greater the probability that the IS will be a success
C) The requirements study determines the probability of success of the proposed project.
D) Testing verifies that apps,interfaces,data transfers,and so on,work correctly under all possible conditions.

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

Project ________ depends on prompt and candid feedback from the project team,while ________ depends on systems and decision rules for managing variances between the project's scope,cost,and schedule.


A) Monitoring;control
B) Management;monitoring
C) Critical path;scope creep
D) Timeline;baseline

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

Critical path is the ________ path of tasks through a project,as shown on a Gantt chart.


A) most complex
B) first
C) longest
D) shortest

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

The financial services sector has been compelled by strict international anti-money-laundering (AML) guidelines that require firms to _________.


A) know your customer
B) implement master data management
C) adhere to project portfolio management
D) demonstrate data consistency and accuracy

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

__________ conversion is the least expensive and highest risk IS conversion strategy because the old system is cut off and the new system is turned on at a certain point in time.


A) Parallel
B) Direct
C) Pilot
D) Phased

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

Monitoring and control processes are intended to occur weekly while the project work is being executed.

A) True
B) False

Correct Answer

verifed

verified

The money already spent on the project,or sunk costs,should be considered in the decision to kill a project that is out of control.

A) True
B) False

Correct Answer

verifed

verified

False

Projects start with an idea that is explained in a business case.If the business case is accepted,a work breakdown structure (WBS)is prepared.

A) True
B) False

Correct Answer

verifed

verified

Calculating economic feasibility in IT projects is straightforward because it is done using standard financial techniques--ROI,NPV,and breakeven analysis.

A) True
B) False

Correct Answer

verifed

verified

A responsibility matrix shows who has primary responsibility and who has support responsibility for the activities listed in the WBS.

A) True
B) False

Correct Answer

verifed

verified

Except in extreme cases,the evaluation of success or failure is ________ because time and cost to complete the project are _________.


A) Subjective;estimates
B) Done by the project manager;fixed
C) Objective;inflexible
D) Done by the project team;set by them

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A

The financial services sector has been compelled by strict international anti-money-laundering (AML)guidelines that require firms to know your customer (KYC).

A) True
B) False

Correct Answer

verifed

verified

True

Controls help to prevent ________,which refer to system development projects that are so far over budget and past deadline that they must be abandoned,typically with large monetary loss.


A) Deficient critical paths
B) runaway projects
C) scope creep
D) missed deadlines

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

During the systems investigation stage,__________ studies are done to assess the skills and the training needed to use the new system.


A) Economic feasibility
B) Technical feasibility
C) Organizational feasibility
D) Behavioral feasibility

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

________ should not be considered in the decision to kill a project.


A) Completed deliverables
B) Project scope
C) Sunk costs
D) SOW

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

Monitoring and control processes should occur _________ while the project work is being executed.


A) weekly or bi-weekly
B) continuously and continually
C) monthly
D) at each milestone

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

Scope creep is the piling up of numerous small delays that by themselves may be manageable,but in aggregate are significant.

A) True
B) False

Correct Answer

verifed

verified

Showing 1 - 20 of 103