Multiple Choice
A) Past experience.
B) Work packages.
C) Task analysis.
D) Time and motion studies.
E) Work breakdown structure.
Correct Answer
verified
Multiple Choice
A) Should be used only for projects that require the same task, group of tasks, or product to be repeated several times
B) Uses several people with relevant experience regarding the task at hand to make time and cost estimates
C) Uses pooled experience of senior and/or middle managers to estimate the total project duration and cost
D) Uses the number of square feet to estimate the total cost and time of the project
E) Uses weighted macro variables or major parameters such as the number of inputs or outputs to estimate the total cost and time of the project
Correct Answer
verified
Multiple Choice
A) They are made by someone who uses experience and/or information from someone else to determine overall project cost and duration.
B) They establish low-cost, efficient methods for completing activities.
C) They typically comes from the people actually doing the work and who are most knowledgeable about the task at hand.
D) Estimates are made at the work package level and then "rolled up" to determine estimates for major deliverables and for the project itself.
E) They can take place after the project has been planned in detail.
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) When the project involves strategic decision making
B) When the project is internal and small
C) When there is a fixed price contract
D) When there is high uncertainty involved in the project
E) When there is an unstable scope
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Estimates should be made by those responsible for the work.
B) Use several people to estimate the same work.
C) Estimates should be based on normal conditions.
D) Estimates should include a normal level of contingency.
E) Estimates should be independent of other projects.
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) Parametric procedures applied to specific tasks
B) Estimates for the WBS work packages
C) Learning curve
D) Template method
E) Range estimates
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Short Answer
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) Labor
B) Direct
C) Direct project overhead
D) General and administrative overhead
E) Salary
Correct Answer
verified
True/False
Correct Answer
verified