An assembly line with 28 activities is to be balanced. The total amount of time required for all 28 activities is 39 minutes. The line will operate for 450 minutes per day. What must the cycle time be to achieve an output rate of 400 units/day?


A) 1.39 minutes
B) 11.54 minutes
C) 1.125 minutes
D) 0.89 minutes

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

All of the following are common objectives of layout studies except


A) Minimize delays in materials handling and customer movement
B) Minimize the number of workstations
C) Provide for good housekeeping and maintenance
D) Maintain flexibility

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

____ classifies parts into families so that cellular layouts can be effectively used.


A) Ergonomics
B) Job enlargement
C) Group technology
D) CRAFT

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

Facility layout is not only concerned with the arrangement of physical facilities, but also the material handling capabilities within the facility.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a disadvantage of virtual teams?


A) Security
B) Working hours
C) Synchronizing calendars
D) Socialization

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Because of precedence relationships, assembly-line efficiencies will generally be very high.

A) True
B) False

Correct Answer

verifed

verified

False

Discuss the advantages and disadvantages of utilizing virtual teams.

Correct Answer

verifed

verified

Advantages:
1. Allow the best possible t...

View Answer

Explain assembly line balancing. Discuss the three types of information needed to balance an assembly line.

Correct Answer

verifed

verified

Assembly line balancing is a technique t...

View Answer

Self-managed teams perform entire jobs, rather than specialized assembly-line work.

A) True
B) False

Correct Answer

verifed

verified

All of the following are limitations to process layout except


A) Higher movement and transportation costs
B) More complicated planning and control systems
C) Longer total processing time
D) Limited range of products

E) A) and C)
F) B) and D)

Correct Answer

verifed

verified

The nine tasks necessary to assemble a vacuum cleaner are listed below. The time to perform each task and the tasks that must immediately precede are also listed. 300 vacuums are needed per hour and 50 minutes per hour are productive. The nine tasks necessary to assemble a vacuum cleaner are listed below. The time to perform each task and the tasks that must immediately precede are also listed. 300 vacuums are needed per hour and 50 minutes per hour are productive.    a.Compute the cycle time per unit in minutes. b.Compute the minimum number of workstations required. c.Use the longest-task-time heuristic to balance the production line. d.Compute the efficiency of the assembly line. a.Compute the cycle time per unit in minutes. b.Compute the minimum number of workstations required. c.Use the longest-task-time heuristic to balance the production line. d.Compute the efficiency of the assembly line.

Correct Answer

verifed

verified

a.Cycle time = 50/300 = .167 minutes per...

View Answer

A ____ layout consists of a functional grouping of equipment or activities that do similar work.


A) Product
B) Process
C) Cellular
D) Fixed position

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Differentiate between a "flow blocking delay" and a "lack of work delay." How can each be reduced?

Correct Answer

verifed

verified

Flow-blocking delay occurs when a work center completes a unit but cannot release it because the in-process storage at the next stage is full. The worker must remain idle until storage space becomes available. Lack-of-work delay occurs whenever one stage completes work and no units from the previous stage are waiting processing. Attempting to "balance" the process by designing the appropriate level of capacity at each workstation can minimize these sources of delay. This is often done by adding additional workstations in parallel. Product layouts might have workstations in series, in parallel or in a combination of both.

A(n) ____ performs entire jobs rather than specialized, assembly line work.


A) Virtual team
B) Self-managed team
C) Natural work team
D) Ergonomic team

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

C

A product requires the following tasks to make it on an assembly line. Assume 7.6 hours per workday and 5 workdays per week. A product requires the following tasks to make it on an assembly line. Assume 7.6 hours per workday and 5 workdays per week.    a.Using only the information given, what would be the maximum output per day that can be achieved? b.Assume that the activities have been assigned to five workstations. What is the line efficiency for a cycle time of 40 seconds? a.Using only the information given, what would be the maximum output per day that can be achieved? b.Assume that the activities have been assigned to five workstations. What is the line efficiency for a cycle time of 40 seconds?

Correct Answer

verifed

verified

a.The minimum cycle time is the maximum ...

View Answer

____ set their own goals and inspect their own work, often hire their own replacements and prepare their own budgets.


A) Virtual teams
B) Enlarged teams
C) Socio-technical teams
D) Self-managed teams

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Cellular layouts are designed according to the functional characteristics of equipment much in the same fashion as process layouts.

A) True
B) False

Correct Answer

verifed

verified

Cycle time in assembly line balancing is the maximum amount of time it takes to process a part at some workstation along the line.

A) True
B) False

Correct Answer

verifed

verified

The production of large goods such as airplanes is best accomplished using a ____ layout.


A) Product
B) Process
C) Cellular
D) Fixed position

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

An assembly line with 28 operations is to be balanced. The total amount of time required for all 28 operations is 39 minutes. The longest operation takes 2.2 minutes and the shortest takes 0.8 minutes. The line will operate for 450 minutes per day. a.Determine the minimum and maximum cycle time. b.What is the maximum output rate that this assembly line can achieve? c.What is the output rate if the cycle time is set at 2.2 minutes?

Correct Answer

verifed

verified

a.The minimum cycle time is the shortest...

View Answer