In project management,crashing an activity must consider the impact on all paths in the network.

A) True
B) False

Correct Answer

verifed

verified

Ethical issues that can arise in projects include gifts from contractors,pressure to mask delays with false status reports,and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.

A) True
B) False

Correct Answer

verifed

verified

A network consists of the following list.Times are given in weeks. A network consists of the following list.Times are given in weeks.    a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path? a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path?

Correct Answer

verifed

verified

(a)Network diagram blured image (b)paths A...

View Answer

What are the three phases of a project? Describe each in a sentence or two.

Correct Answer

verifed

verified

The three phases are planning,scheduling...

View Answer

Which of the following statements regarding critical paths is true?


A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

A simple CPM network has three activities,A,B,and C.A is an immediate predecessor of B and of C.B is an immediate predecessor of C.The activity durations are A=4,B=3,C=8.


A) The critical path is A-B-C,duration 15.
B) The critical path is A-C,duration 12.
C) The critical path is A-B-C,duration 13.5
D) The critical path cannot be determined without knowing PERT expected activity times.
E) The network has no critical path.

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

The network analysis method that allows activity times to vary is ________.

Correct Answer

verifed

verified

PERT or Pr...

View Answer

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day) ?


A) 98
B) 112
C) 120
D) 124
E) 220

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

A code of ethics especially for project managers:


A) has been established by the Project Management Institute.
B) has been formulated by the Federal government.
C) has been formulated by the World Trade Organization.
D) is inappropriate,since everyone should use the same guidance on ethical issues.
E) does not exist at this time.

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

The beta distribution is used in project management to:


A) determine which activity should be crashed.
B) calculate the probability that a project will be completed within its budget.
C) calculate expected activity times.
D) calculate slack for activities on the critical path.
E) none of the above

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Describe the differences between a Gantt chart and a PERT/CPM network.

Correct Answer

verifed

verified

The differences between a Gant...

View Answer

What is the basic difference between PERT and CPM?

Correct Answer

verifed

verified

The basic difference between P...

View Answer

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.

A) True
B) False

Correct Answer

verifed

verified

Shortening the project's duration by deleting unnecessary activities is called "project crashing."

A) True
B) False

Correct Answer

verifed

verified

The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.

Correct Answer

verifed

verified

Contract requirements state that a project must be completed within 180 working days,or it will incur penalties for late completion.Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400.What is the probability that the project will be completed before the late-payment deadline?


A) 0.0401
B) 0.4599
C) 0.8056
D) 0.9599
E) near 1.0000,or almost certain

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

Which of the following statements regarding time-cost tradeoffs in CPM networks is false?


A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?

Correct Answer

verifed

verified

Add the variances of the activ...

View Answer

Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.Given the project table below calculate the crash cost for 8 hours of time-savings.Suppose Pirmin calls the customer and asks for a project extension,reducing the amount of time he needs to crash.Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings. Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project.Given the project table below calculate the crash cost for 8 hours of time-savings.Suppose Pirmin calls the customer and asks for a project extension,reducing the amount of time he needs to crash.Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings.

Correct Answer

verifed

verified

blured image The critical path is ABCEFGH with a tim...

View Answer

Identify several advantages of using PERT (and CPM).

Correct Answer

verifed

verified

The advantages include (1)its usefulness...

View Answer