Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.
Correct Answer
verified
Multiple Choice
A) The critical path is A-B-C,duration 15.
B) The critical path is A-C,duration 12.
C) The critical path is A-B-C,duration 13.5
D) The critical path cannot be determined without knowing PERT expected activity times.
E) The network has no critical path.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) 98
B) 112
C) 120
D) 124
E) 220
Correct Answer
verified
Multiple Choice
A) has been established by the Project Management Institute.
B) has been formulated by the Federal government.
C) has been formulated by the World Trade Organization.
D) is inappropriate,since everyone should use the same guidance on ethical issues.
E) does not exist at this time.
Correct Answer
verified
Multiple Choice
A) determine which activity should be crashed.
B) calculate the probability that a project will be completed within its budget.
C) calculate expected activity times.
D) calculate slack for activities on the critical path.
E) none of the above
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) 0.0401
B) 0.4599
C) 0.8056
D) 0.9599
E) near 1.0000,or almost certain
Correct Answer
verified
Multiple Choice
A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Showing 21 - 40 of 124
Related Exams